  • The Trout Creek Recreation Center parking lot asphalt and curbs will be replaced starting September 3, 2021 through mid-October.

WHY THIS PROJECT?

  • The parking lot is in need of an upgrade to enhance membership and guest use.

WHAT ARE THE IMPACTS?

  • Construction will occur from September 3 through mid-October 2021. Timeline includes:
    • September 3-11: Set offset stakes, sawcut in front of new curb, curb demo and prep for new concrete
      • Southeast side of the property curb and far east side parking by Northwoods (this will not hinder ingress and egress)
      • Complete prep work by September 11
    • September 27 – October 6: Concrete form pour and finish with machine
    • Week of Oct.  4: Pulverize all remaining pavement, fine grade & prep for new paving
    • Week of Oct. 11: Pave and stripe all pavement markings

WHAT IS THE TIMELINE?

  • This project should be complete by mid-October 2021.

WHAT IS THE TOTAL COST?

  • The total cost is anticipated to be $411,000.